23 Dec 2018
A big push this week to get some major tasks complete prior to the Christmas break. You’ll see the new driveway at the front of the church which is an exciting addition as well as scaffolding to the sides of the building which will allow the preparation for external painting and installation of new gutters.
Works undertaken by the builder this week
Fire exit door fitted; glazing fitted to front doors; coffee servery bi-fold windows fitted; concrete driveway completed; external scaffolding installed; installation of electrical metering board.
Coming up this week
The builder will have a break over Christmas returning in earnest on 7th January. We will, however, see a couple trades come and go to do some odd jobs over the break including new gutters and the kitchen vinyl which will be installed between Christmas and New Year.