28 October 2018
Hall and Forecourt Project update
Thanksgiving at St Stephen’s is a tradition that allows us to look back at God’s goodness, look outward to how His blessing can flow through us, and look forward to His promise of what is to come. As the current building project develops for this Thanksgiving Sunday, we are excited for the way you, His church in Coorparoo, are sowing into His local mission.
A reminder for those who drop off passengers at the front of the church that the entry road will not be available to us until the end of the project in early 2019. Please re-familiarize yourself with the temporary drop off arrangements on the notice board.
Works undertaken this week by builder:
Installation of structural steel for bi-fold doors; waterproofing to wet areas; detailed excavation for courtyard walls and planter box footings, lay reinforcement and pour concrete; subframing to kitchen windows and windows delivered
Works undertaken this week by St Stephens and Hall Committee:
Preparations for alternative drop off assistance; meeting with northern neighbours; preparations and planning for new signage
Coming up this week:
Tiling to amenities and entry; blockwork walls to courtyard; fitting new aluminium windows to kitchen and front door; 2nd fix carpentry; re-install VJ cladding to east wall; internal painting commences; carpets to meeting rooms; kitchen joinery manufacture