2 September 2018
Hall and Forecourt Project update
The builder has continued their rapid progress this week. We took a peek inside when we meet with the builder on Thursday.
Works undertaken this week by the builder:
Internal wall framing modifications for kitchen, toilets and meeting rooms; electrical and plumbing services commence rough-in; excavation for retaining walls on northern boundary continuing – modified to suit neighbours brick walls; re-stump north east corner of hall; investigate extent of timber rot.
Works undertaken this week by St Stephens and Hall Committee:
Finalise selection/purchase of appliance and equipment for kitchen; review and finalise kitchen layout, finishes and colours; review shade sail colours and
external finishes selections.
Coming up next week:
Offsite fabrication of joinery, windows and electrical switchboard; commence re-lining walls; electrical and plumbing services rough-in; commence installation wall linings; remove windows.