The courtyard is taking shape!

St Stephen’s Hall and Forecourt Redevelopment Project

18 November 2018

Hall and Forecourt Project update

The builder has started the process of finishing components of the new work.  It is incredibly exciting to see the little details that the Hall Committee have pained over actually being fitted out.

Works undertaken this week by builder

Tiling of amenities and entry area complete; timber trims to door/window frames, skirting; re-cladding walls; commence kitchen joinery installation; footings for concrete seats to courtyard; place soil to main planter boxes; backfill to ramp.

Coming up this week

Complete concrete seats to courtyard; commence external concrete slabs; commence internal painting.

 

The courtyard is taking shape!