26 August 2018
The builder has continued their rapid progress this week.
We are looking forward to taking a peek inside next week when we meet with the builder on Thursday!
Works undertaken this week by builder:
Internal demolition continuing; asbestos removal; commence wall framing modifications; decommission/remove existing redundant electrical and plumbing services; excavation for retaining walls on northern boundary continuing; removal of rubble from site; delivery of second disabled accessible temporary toilet for
church use.
Works undertaken this week by St Stephens and Hall Committee:
Temporary kitchen complete; review and adjust internal and external finishes and colours; select and/or purchase kitchen equipment
Coming up this week:
Commence offsite fabrication of joinery, windows and electrical switchboard; electrical and plumbing services rough-in; commence installation wall lining.