St Stephen’s Hall and Forecourt Redevelopment Project

26 August 2018

The builder has continued their rapid progress this week.

We are looking forward to taking a peek inside next week when we meet with the builder on Thursday!

Works undertaken this week by builder:

Internal demolition continuing; asbestos removal; commence wall framing modifications; decommission/remove existing redundant electrical and plumbing services; excavation for retaining walls on northern boundary continuing; removal of rubble from site; delivery of second disabled accessible temporary toilet for
church use.

Works undertaken this week by St Stephens and Hall Committee:

Temporary kitchen complete; review and adjust internal and external finishes and colours; select and/or purchase kitchen equipment

Coming up this week:

Commence offsite fabrication of joinery, windows and electrical switchboard; electrical and plumbing services rough-in; commence installation wall lining.